In Holly Springs, a subdivision has to win its share of the town's wastewater capacity before its engineering plans are even accepted. The town's Water Resource Management Policy says Holly Springs will not accept civil construction drawings or approve water and sewer extension permits until the project's utility allocation has been approved. Any project that needs to connect to town sewer files a Utility Allocation Request, and Town Council approves it as a separate decision from the zoning case.
That one rule explains a lot about the Holly Springs market for a buyer comparing south Wake towns. New homes arrive in measured portions tied to a fixed yearly release of capacity, not whenever a builder is ready. Because of that, the next year of new-home supply depends more on the town's July allocation release and on council allocation votes than on any monthly median.
The policy took effect July 1, 2023, and it covers any new project, or any change to an existing project's utility demand, that needs a council decision or a staff approval. The request goes in with the project's first Unified Development Ordinance application and moves through review alongside it. In order, a new detached subdivision goes through these steps:
That fifth step sets the pace. A 300-lot community cannot get all of its sewer capacity in one year under this policy. It moves forward in sections. A phase within 10% of the 75-lot limit can get an exception from the Director based on design constraints or build-out.
The town's housing staff have put the overall timing in numbers. The draft Affordable Housing Action Plan describes average development review of about 18 months and proposes cutting that to 12 months for qualifying projects.
The town releases available capacity once per fiscal year, in the first week of July. Before any subdivision gets a share, the release is split into buckets:
| Category | Share of the annual release | Floor | What draws from it |
|---|---|---|---|
| Operational Reserve | 30% | At least 33,000 gallons per day | Significant public facility projects and economic development projects |
| Residential | Up to 70% of what remains after the reserve | At least 46,900 gallons per day | Detached homes, attached homes, apartments |
| Non-Residential | 30% of what remains after the reserve | At least 20,100 gallons per day | Projects the UDO defines as non-residential |
The residential bucket is split again. In a given year, no more than 20% of the available residential flow can go to attached homes or apartment developments. Leftover residential flow at the end of the fiscal year rolls into the next year.
The policy also has an accounting rule. Allocated flow is not treated as actual flow on the system until a certificate of occupancy is issued or a water meter is installed. So capacity is committed to a project on paper years before anyone lives in those homes, and every approved but unbuilt subdivision counts against what's left.
None of the reporting we reviewed gave the amount released in July 2026 for fiscal year 2026–27 or the size of the waiting list. Anyone who claims to know how many lots Holly Springs will approve this year is estimating.
The most recent town-level sales figures come from deed records, not MLS data. In August 2026, according to Wake County Register of Deeds data summarized by Holly Springs Update, the three south Wake towns looked like this:
| Town, August 2026 | Recorded home sales | Median sale price | Highest residential sale |
|---|---|---|---|
| Apex | 141 | $631,500 | $2.04 million, new build on Weston Farm Way |
| Fuquay-Varina | 92 | $447,500 | $1.124 million, new build on Granary Farm Lane |
| Holly Springs | 26 | $744,000 | $1.115 million on Rambling Oaks Lane |
| Wake County overall | n/a | $440,000 | n/a |
Holly Springs made up about one in ten of the 259 sales across the three towns that month, yet it had the highest median of the three. A 26-sale month is a small sample, and one month of deed data can't support a trend or a cause. What the figures do show is a market with a thin flow of closings, which fits a town where new-home supply is released in phases. The draft affordability plan gives a longer view: Holly Springs sale prices are up 59% since 2019, and the 2025 single-family median was $565,000. The plan's 2025 median and August's $744,000 come from different data sources and periods, so the gap between them isn't a valid comparison.
For a buyer, a limited new-home pipeline means resale listings face fewer new-build alternatives here than in a town where large subdivisions can open in one go. It also means a new community you tour may be selling a phase that already has its allocation while later phases are still waiting on a future July release.
Changes in supply show up as council agenda items well before they appear in the sales data. Three recent items show how that works:
The action plan relies on incentives, not requirements. The town attorney told council that municipalities cannot base zoning decisions on anticipated home sale prices. The plan instead proposes an incentive zoning policy, a faster approval track for qualifying projects, and a pilot repair grant program for existing homeowners. The faster track would change review time, which is a separate question from how much sewer capacity there is. A faster review still ends at the same allocation buckets.
The bigger change is under construction at the Utley Creek Water Reclamation Facility. The plant treats up to 6 million gallons of wastewater per day now and is being expanded to 8 million. The project's total cost is $219 million. At its Jan. 20, 2026 meeting, council approved a $153.16 million Phase 2 construction contract with Adams Robinson Enterprises, plus $15.3 million for construction administration and inspection and $16.8 million in contingency. Town leaders called the expansion necessary for the town to keep approving new development.
The North Carolina Local Government Commission approved $135 million in revenue bonds for Holly Springs projects on March 3, 2026. The state's release projected water and sewer rate increases of 9% to 15% through fiscal year 2031. The capacity expansion is paid for through utility revenue, and that cost shows up on household water and sewer bills.
On timing, the town's September 2024 procurement schedule estimated substantial completion at the beginning of the second quarter of 2028. That date was an estimate, and we found no newer confirmed schedule. Several other projects have target dates around the same window:
The allocation policy also places economic development projects in the Operational Reserve bucket, separate from the residential share. Under the policy, job-producing projects and subdivisions draw from different shares of the same annual release.
The policy applies to new projects and to changes in an existing project's utility demand. A resale home that's already connected isn't going through the allocation process. It does compete with new construction that the allocation process limits.
Council keeps the right to review, modify or deviate from the policy at its discretion, including how capacity is divided among categories. The version described here took effect July 1, 2023.
It's based on 26 recorded deed transactions in a single month, so treat it as a snapshot. Prices on a specific street or in a specific phase can differ a lot from it.
If you're comparing south Wake towns and want to know which Holly Springs communities have allocated phases selling now and which are still waiting for capacity, Kingsley Real Estate can go through the council record and the comps with you. If you already own in Holly Springs, start with Get Your Instant Home Valuation to see where your home stands while new-home supply is limited.
This article is general information, not legal, tax or financial advice. Consult a qualified professional about your situation.
Stay up to date on the latest real estate trends.
We pride ourselves in providing personalized solutions that bring our clients closer to their dream properties and enhance their long-term wealth.